Answer: A-Single-time estimate
CPM requires a single-time estimate.
Solution:
CPM is the acronym for Critical Path Method. CPM is an activity-oriented technique that focuses on cost optimization. CPM requires a single-time estimate and it is a deterministic model. In contrast to this, PERT is an event-oriented technique and requires three times the estimate.