Pre Tender Stage Requires
By BYJU'S Exam Prep
Updated on: September 25th, 2023
Pre-tender stage requires
a. Acquisition of land
b. Selection of site
c. finalisation of designs and preparation of estimate
d. all the above
Find the correct answer to the question from the options provided above.
Table of content
Answer- D. All the above
The pre-tender stage requires the acquisition of land, selection of site and finalisation of designs and preparation of estimate.
Solution
Tendering is the process to invite contractors for a project in which many contractors placed their bids to take the project. Bids are based on the requirements of projects which are mentioned by the company.
Pre tender stage involves activities such as
- Preparation of detailed scope of work
- Preparation of tender drawings
- Land acquisition
- Estimation of cost of work
- Site survey
☛ Related Questions:
- Hydrographic surveys deal with the mapping of
- The water shed canal is also called
- As the percentage of steel increases
- Workability of concrete is measured by
- for a quick soil