Answer: D. All of the above
A construction schedule is prepared after collecting the number of operations, output of labour and machinery.
Solution
A construction schedule is a timeline for every event that has to be completed in a construction project. It is the most fundamental part of the planning phase of any construction project. It defines the roles of every member associated with the project and all the different types of resources required.
A construction schedule is prepared after collecting the number of operations, output of labour and machinery, quantity of various items required and many other things.
☛ Related Questions:
Comments
write a comment