A Construction Schedule Is Prepared After Collecting

By BYJU'S Exam Prep

Updated on: September 25th, 2023

A construction schedule is prepared after collecting

  1. Number of operations
  2. Output of labour
  3. Output of machinery
  4. All of the above

Answer: D. All of the above

A construction schedule is prepared after collecting the number of operations, output of labour and machinery.

Solution

A construction schedule is a timeline for every event that has to be completed in a construction project. It is the most fundamental part of the planning phase of any construction project. It defines the roles of every member associated with the project and all the different types of resources required.

A construction schedule is prepared after collecting the number of operations, output of labour and machinery, quantity of various items required and many other things.

☛ Related Questions:

Our Apps Playstore
POPULAR EXAMS
SSC and Bank
Other Exams
GradeStack Learning Pvt. Ltd.Windsor IT Park, Tower - A, 2nd Floor, Sector 125, Noida, Uttar Pradesh 201303 help@byjusexamprep.com
Home Practice Test Series Premium