Question 1

In a CPM network the activity is non critical if

Question 2

With reference to the network shown in Fig. given below, which statement is incorrect?

Question 3

The earliest date and the latest date of events 3 and 10 are given in figure below. Activity E is connecting both the events and its duration is 10 weeks. The independent float of the activity is?

Question 4

Consider the following activity i-j of certain network. The value of Total Float*Free float*Independent Float is equal to

Question 5

The activity details of a project are given below:

The estimated minimum time (in days) for the completion of the project will be________

Question 6

A project consists of 8 activities as shown in the table. The project duration is