Time Left - 06:00 mins
ESE 2021 Technical Quiz || Network Analysis - PERT
Attempt now to get your rank among 284 students!
Question 1
The duration of any activity in case of a PERT programme is calculated as a weighted average of three time estimates namely the optimistic time to, the pessimistic time tp and the most probable time tm, which is given as
Question 2
Which one of the following is a point in time when certain conditions have been fulfilled, such as the start or completion of one or more activities?
Question 3
The difference between the latest allowable time and earliest expected time of an event is known as
Question 4
The area under -distribution curve is divided into two equal parts by
Question 5
PERT calculations yield a project length of 70 weeks with a variance of 9 weeks. The number of weeks required to complete the project with a probability of 95% (probability factor for 95% = 1.647) is
- 284 attempts
- 0 upvotes
- 2 comments
May 17ESE & GATE CE