Question 1

Which one of the following techniques in not covered in Project Network Analysis?

Question 2

Consider the following activity for the total project:

To total project duration for the critical path will be

Question 3

Consider the following statements:
1) Total float can affect all activities in the chain.
2) Free float can affect only the preceding activities.
3) Independent float affects only the particular concerned activity.
Which of these statements/are correct?

Question 4

What is the time by which the completion of an activity can be delayed without affecting the start of succeeding activities, called?

Question 5

Consider the following statements pertaining to CPM network analysis:
1) It is event-oriented method.
2) It is activity-oriented method.
3) Time and cost are controlling factors.
4) Time alone is controlling factor.
Which of these statements are correct?