AE & JE CE Quiz Estimating, Costing and Valuation Booster Quiz -1
Attempt now to get your rank among 259 students!
Question 1
For estimation of painting area of corrugated steel sheets, percentage increase in area above the plain area is ______.
Question 2
The plan of a building is in the form of a rectangle with centre line dimensions as The thickness of the wall in super structure is 0.30 m. What is the floor area of the building?
Question 3
In the analysis of rates, the profit for the contractor is generally taken as ______.
Question 4
When actual cost of construction plus certain profit is paid to the contractor then such a contract is known as ________.
Question 5
Read the following statements:
1) Direct cost increases with the project duration.
2) Indirect cost decreases with the project duration.
3) Rescheduling the activities so that the peak resource requirement does not exceed the available resources is called Resource smoothing.
Which of the above statements are incorrect?
1) Direct cost increases with the project duration.
2) Indirect cost decreases with the project duration.
3) Rescheduling the activities so that the peak resource requirement does not exceed the available resources is called Resource smoothing.
Which of the above statements are incorrect?
Question 6
In PERT analysis, the time estimates of activities follow
Question 7
Which of the following is a dummy activity?
Question 8
The value of the dismantled material less the cost of dismantling is called _______.
Question 9
Capitalized value of a property is the product of ___________
Question 10
Working out the exact quantities of various items of work is known as ______.