RVUNL ME || Industrial Engineering || Quiz 5

Attempt now to get your rank among 185 students!

Question 1

The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is known as

Question 2

PERT has following time estimate ________.

Question 3

The optimistic, most likely and pessimistic time estimates of an activity are given as 8 days, 24 days and 44 days respectively. The standard deviation of the activity is

Question 4

A dummy activity _________.

Question 5

Time estimates of a project activity are:
topoptimistic time = 10 days.
tml, most likely time = 15 days.
tpcs, pessimistic time =22 days.
Variance in days for this activity as per BETA distribution is:

Question 6

The earliest occurrence time for event '1' is 8 weeks and the latest occurrence time for event' I' is 26 weeks. The earliest occurrence time for event '2' is 32 weeks and the latest occurrence time for event '2' is 37 weeks. If the activity time is 11 weeks, then the total float will be: