Question 1

A scaled drawing of the proposed construction site showing all the relevant features such as entry and exit points to the site, storage area for materials, toilets workers quarters, etc. is called

Question 2

Williams-Steiger Occupational Safety and Health Act (OSH Act) was passed in the year

Question 3

The event or events that immediately come before another event without any intervening events are called _____events to that event.

Question 4

Injury frequency rate per lakh of man-hours worked is calculated as:

Question 5

Critical path is_____.

Question 6

For the network shown, the estimated time in days for each activity is shown in the network diagram. The probability of completing the project in 45 days would be:

The values of Z and the corresponding probability are given in the table: