Question 1

It is estimated that an activity can be assigned an optimistic duration of 16 days, a pessimistic duration of 28 days and a most likely duration of 19 days. What is the expected duration for this activity?

Question 2

For a project just a following data is given, what can be deduced from the figure

Question 3

The maximum possible time in which activity can be done becomes 7 time the minimum possible time. If under normal working condition 17 days required to perform the same task, then expected time to complete activity

[σ = 6]

Question 4

Choose correct state

i) As uncertainty increase variance decrease.

ii) Greater the standard deviation lesser the variance

Question 5

For a network diagram shown below

If both x, y has even or odd number, then probability factor will be 84.13% else 15.87%.

σ = 8 for 1 2 and 2 5

σ = 7 for 1 3, 3 4, 4 5

What is the critical path?

Question 6

A project has duration of 43 days and a variance of 34. What is the ratio of maximum and minimum time of completion for this project?

Question 7

For a network diagram shown in figure

If standard deviation is X for entire project. If Scheduled time is 22 days and probability factor is 3 then value of X is