PERT -Quiz Starter Quiz
Attempt now to get your rank among 64 students!
Question 1
It is estimated that an activity can be assigned an optimistic duration of 16 days, a pessimistic duration of 28 days and a most likely duration of 19 days. What is the expected duration for this activity?
Question 2
For a project just a following data is given, what can be deduced from the figure
Question 3
The maximum possible time in which activity can be done becomes 7 time the minimum possible time. If under normal working condition 17 days required to perform the same task, then expected time to complete activity
[σ = 6]
Question 4
Choose correct state
i) As uncertainty increase variance decrease.
ii) Greater the standard deviation lesser the variance
Question 5
For a network diagram shown below
If both x, y has even or odd number, then probability factor will be 84.13% else 15.87%.
σ = 8 for 1 → 2 and 2 → 5
σ = 7 for 1 → 3, 3→ 4, 4 → 5
What is the critical path?
Question 6
A project has duration of 43 days and a variance of 34. What is the ratio of maximum and minimum time of completion for this project?
Question 7
For a network diagram shown in figure
If standard deviation is X for entire project. If Scheduled time is 22 days and probability factor is 3 then value of X is