Time Left - 15:00 mins
Industrial Engg Golden PYQ Quiz 7
Attempt now to get your rank among 35 students!
Question 1
The forecast for the monthly demand of a product is given in the table below.
The forecast is made by using the exponential smoothing method. The exponential smoothing coefficient used in forecasting the demand is
Question 2
The demand of a certain part is 1000 parts/year and its cost is ₹1000/part. The orders are placed based on the economic order quantity (EOQ). The cost of ordering is ₹100/order and the lead time for receiving the orders is 5 days. If the holding cost is ₹20/part/year, the inventory level for placing the orders is _________ parts (round off to the nearest integer).
Question 3
Consider a single machine workstation to which jobs arrive according to a Poisson distribution with a mean arrival rate of 12 jobs/hour. The process time of the workstation is exponentially distributed with a mean of 4 minutes. The expected number of jobs at the workstation at any given point of time is ________ (round off to the nearest integer).
Question 4
Processing times (including setup times) and due dates for six jobs waiting to be processed at a work centre are given in the table. The average tardiness (in days) using shortest processing time rule is _________(correct to two decimal places).
Question 5
A project starts with activity A and ends with activity F. The precedence relation and durations of the activities are as per the following table:
The minimum project completion time (in days) is _________.
The minimum project completion time (in days) is _________.
Question 6
The minimum value of such that:
is __________.
- 35 attempts
- 1 upvote
- 0 comments
Nov 13ESE & GATE ME