Question 1
Dummy activities are the activity which _______.
Question 2
Critical path lies along the activities having total float
Question 3
In CPM network critical path denotes the ___________.
Question 4
The activity that can be delayed without affecting the execution of the immediate succeeding activity is determined by ___________.
Question 5
CPM analysis presumes that______.