Time Left - 15:00 mins

GATE 2022 ME: Industrial Engineering Quiz - 8

Attempt now to get your rank among 487 students!

Question 1

In Materials Requirement Planning, if the inventory holding cost is very high and the setup cost is zero, which one of the following lot sizing approaches should be used?

Question 2

Which of the following is not an input for material requirement planning?

Question 3

A machine is used for turning operation and it takes 30 minutes to machine the component. Efficiency of the machine is 80% and scrap is 25%. The desired output is 1200 pieces per week. Considering 40 hours per week and 50 weeks in a year. The number of machine required in a year______.

Question 4

A production line is said to be balanced when

Question 5

A 5 station assembly line has allotted times 7, 9, 8, 6 and 5 minutes respectively. What is the balance delay __________?

Question 6

An electronic equipment manufacturer has decided to add a component subassembly operation that can produce 80 units during a regular 8-hour shift. This operation consists of three activities as below:
Description: D:\GradeStack Courses\GATE Tests (Sent by Ravi)\GATE ME 18-Mar\GATE-ME-2004_files\image302.png
For line balancing the number of work stations required for the activities M, E and T would respectively be __________.

  • 487 attempts
  • 0 upvotes
  • 0 comments
Oct 3ESE & GATE ME