Time Left - 06:00 mins

Estimating, Costing and Valuation Booster Quiz -10

Attempt now to get your rank among 227 students!

Question 1

When only some selected contractors are invited to place bid for the project, this type of tendering process is known as

Question 2

In an excavation of 3,000 cubic meter of common earth for a canal project, 6 men can be effectively employed on the job. If an output of a man is taken as 100 cubic meter per day, the duration of excavation activity will be

Question 3

What is the number of bricks required in constructing a wall of length 9.45 m, height 3.15 m and thickness 35 cm

Question 4

Calculate the number of cement bags per 10 cum required for RCC work in slab with cement concrete (1:2:4).

Question 5

The estimated quantity of cement and sand in plastering 80 sqm area of wall with 10 mm thick plaster with 1:6 cement mortar. (Assume no wastage and volume of dry mortar is 1.25 times more than of wet mortar)

Question 6

Which one of the following statements is not correct?

Question 7

A construction equipment has a useful life of 10 years after which it is to be replaced by a new one. If the interest rate is 8%, what is the nearest value of the sinking fund factor:

Question 8

Statement (I): Earnest money deposit (EMD) is the money required to be submitted by the contractor on allocation of the tender to him/his firm.

Statement (II): EMD is a type of security against the possibility of contractor denying the execution of work on the allocation of tender to him/his firm.

Question 9

What is unit of measurement and units of payment for woodwork of doors and window fitting.

I. Unit of measurement = Number

II. Unit of payment = Per number

III. Unit of measurement = sqm

IV. Unit of payment = per sqm

Question 10

A construction concrete mixer of capacity 0.9 m3 is used and the mixer discharges the entire batch of concrete into a single hopper. The time per cycle for charging, mixing and discharging may be taken as 1.5 minutes and lost time may be taken as 0.15 minutes. The number of batches per hour is equal to: