ESE 2022 CE Technical Quiz 17
Attempt now to get your rank among 273 students!
Question 1
I.
II.
III.
IV.
Question 2
A construction concrete mixer of capacity 0.9 m3 is used and the mixer discharges the entire batch of concrete into a single hopper. The time per cycle for charging, mixing and discharging may be taken as 1.5 minutes and lost time may be taken as 0.15 minutes. The number of batches per hour is equal to:
Question 3
Question 4
Question 5
Question 6
Following date is given for a active sludge process of waste water treatment plant :
Waste water flow = 0.6m3/s
Influent BOD = 50 mg/l
Efficient BOD = 5 mg/s
Volume of aeration tank = 1000 m3
MLSS = 3600 mg/l
MLVSS = MLSS/1.2
Compute F/M ratio (day-1)
Question 7
Question 8
Question 9
Question 10
1. Sight distance available on the road to a driver at any instant depends on the height of the object above the road surface and height of the driver's eye above the road surface.
2. IRC has suggested the height of the object as 0.15 m and the height of the driver's eye as 1.2 m above the road surface
3. Sight distance depends upon the total reaction time of the driver and speed of the vehicle
4. Stopping sight distance will be more in case of downward gradient
Correct statement(s) is/are:
- 273 attempts
- 0 upvotes
- 0 comments
Tags :
ESE & GATE CEGeneral