ESE 2022 CE Technical Quiz 13

Attempt now to get your rank among 219 students!

Question 1

A city of population 2 Lakh discharges sewage with dry sludge content of 0.050 per capita per day. The raw sludge is to be digested in a sludge digestion tank. The moisture content and specific gravity of the wet sludge is 98% and 1.03 respectively. Volume of wet sludge produced (in m3/day) is:

Question 2

Which of the following characteristics of an extended aeration process is/are correct as compared to conventional activated sludge process:

1. Lesser F/M ratio

2. More sludge age

3. Lesser sludge produced

4. More volume required

Question 3

Arrange the following Bogue’s compound in the increasing order of their binding property

1) C3S

2) C2S

3) C3A

4) C4AF

Question 4

Arrange the following Bogue’s compound in their decreasing order of Rate of hydration.

1) C3S

2) C2S

3) C4AF

4) C3A

Question 5

Match the following with the Bogue’s compound in list I and the time required for hydration process in days List II

Question 6

Direction: In the following question consists of two statements Assertion(A) and Reason(R). You have to read the statements carefully and select the answers to these questions using the options below.
Assertion (A): I-section is preferred to rectangular section for resisting bending moment.
Reason(R): in I-section more than 80% of bending moment is resisted by flanges only.

Question 7

Statement (I): Price escalation clause is inserted in all contracts irrespective of contract amount.

Statement (II): The rationale for price escalation clause is to compensate the contractor due to fluctuation in cost of material, fuel and labour.

Question 8

A small project, consists of seven activities in the activity on node diagram as shown in the figure above.

The duration of these of activities, in days and the predecessor relationship are shown.

What is the minimum duration in days required to complete the entire project?

Question 9

A linear project in split into six identical activities each having a, m, and b durations of 14, 18 and 20 days, which results in the standard deviation of the duration for the complete project beings x1 days. As an alternative attempt at project planning, The earlier six activities are clubbed as (1st and 2nd), (3rd and 4th) and (5th & 6th), Thus, needing to consider only three (now modified) activities and the standard deviation of the duration for the complete project is now repeated as X2 days. What will be the ratio ?

Question 10

In the following project network, free float for activity 5-6 is?