The total expected demand for raw material during each time period without regard the inventory on hand is referred as _________.
Question 2
The basic difference between MRP and MRP-II is __________.
Question 3
The symbol used for inspection and storage in work study respectively, are ___________.
Question 4
A time standard for a data entry clerk is to be set. A job rated at 120 % and takes 30 second to enter each records and the allowances are 15 %. What is the normal time __________?
Question 5
Fifty observations of a production operation revealed a mean cycle time of 10 min. the worker was evaluated to be performing at 90% efficiency. Assuming the allowances to be 10% of the normal time, the standard time (in seconds) for the job is_______.