What is the particular task performance in CPM, known as

  1. Dummy
  2. Event
  3. Activity
  4. Contract

Answer: C. Activity

The particular task performance in cpm is known as activity

Solution

An activity is considered as the particular task performance in CPM. An activity is the part of the project which consumes both time and resources. Activity is represented as an arrow in the project

  • Dummy Activity is the type of activity which neither takes any resources nor time to complete it.
  • Event is a node of the completion or starting of an activity. Event also does not take any time or resources to occur.