The Particular Task Performance in CPM is Known

By Ruchika|Updated : July 18th, 2022

The particular task performance in CPM is known?

  1. Dummy 
  2. Activity
  3. Event
  4. Contract

Answer: B (Activity)

The Particular Task Performance in CPM is known

The particular task performance in CPM is known as Activity.

Activity : 

An activity is a physically identifiable part of a project, which consumes both time and resources. 

Activity is represented by an arrow in a network diagram. The head of an arrow represents the start of the activity and the tail of the arrow represents its end. 

The activity description and its estimated completion time are written along the arrow. 

Activity in the network can be represented in a number of ways:

 (i) by numbers of its head and tail events (i.e. 10-20 etc.), and 

(ii) by a letter code (i.e. A, B etc.). 

All those activities, which must be completed before the start of the activity under consideration, are called their predecessor activities. All those activities, which have to follow the activity under consideration, are called its successor activities.

Summary

The Particular Task Performance in CPM is known

The particular task performance or task performance of a specific task in CPM is known as Activity.