The first method invented for planning projects was-

  1. Bar chart method
  2. Milestone chart
  3. Critical path method (CPM)
  4. Programme Evaluation and Review Technique (PERT)

Answer: A. Bar chart method

The first method invented for planning projects was the bar chart method.

Solution

The first method invented for planning projects was the bar chart method which was introduced by Henry Gantt around the year 1900 A.D. Bar chart is therefore also referred to as Gantt Chart. A bar chart is a graphical representation of activity v/s time where the horizontal axis represents time duration and the vertical axis represents activities.