The Critical Activity Has
By BYJU'S Exam Prep
Updated on: September 25th, 2023
The critical activity has-
- Maximum Float
- Minimum Float
- Zero Float
- None of these
Answer: C. Zero Float
Table of content
The critical activity has zero float.
Solution
In CPM analysis there are three types of activity based on their float.
Sub-Critical activity: Sub-critical activities are those activities that are occurring earlier than the scheduled time.
- Sub-critical activity has a positive float.
- Sub-critical activities have more than sufficient resources.
Critical activity: Critical activities are those activities that are occurring just on time.
- The critical activity has zero float.
- Critical activities have just sufficient resources.
Super Critical activity: Super critical activities are those activities that are occurring later than the scheduled time.
- Super critical activity has negative float.
- Super critical activities have less than sufficient resources.
- Super critical activities require more resources to complete on time.