SSC JE 2019-20: Technical Quiz 3

Attempt now to get your rank among 1328 students!

Question 1

The value of wobble correction factor varies from

Question 2

The number of unit hydrographs needed to produce S-curve is

Question 3

The maximum error (mm) on the drawing should not be greater than _________

Question 4

Which of the following bonding is responsible to combine the silica-gibsite sheet in kaolinite clay mineral?

Question 5

The cement becomes useless if its absorbed moisture content exceeds

Question 6

In which of the following unit kinematic viscosity of fluid is measured?

Question 7

Which of the following dimension represents the pressure?

Question 8

Calculate the cost of the plastering required for a wall  of 4 m long, 3.5 m high and 300 mm thick, if the rate of plastering is Rs. 12 per square meter. (Assume both side plastering is done)

Question 9

The least suitable water for irrigation is

Question 10

Creep losses are generally_______ of initial prestressing force.