Pre Tender Stage Requires

By Mohit Uniyal|Updated : July 8th, 2022

Pre-tender stage requires

a. Acquisition of land
b. Selection of site
c. finalisation of designs and preparation of estimate
d. all the above

Find the correct answer to the question from the options provided above.

Answer- D. All the above

The pre-tender stage requires the acquisition of land, selection of site and finalisation of designs and preparation of estimate.

Solution

Tendering is the process to invite contractors for a project in which many contractors placed their bids to take the project. Bids are based on the requirements of projects which are mentioned by the company. 

Pre tender stage involves activities such as

  • Preparation of detailed scope of work
  • Preparation of tender drawings
  • Land acquisition
  • Estimation of cost of work
  • Site survey